top of page

12-15 18 20-22 25-29 November 2-6 9-13 16-17 December 2013

START DATE

END DATE

21-Feb-14

STIFTUNG SALLE MODULABLE and RUTLI STIFTUNG vs. BUTTERFIELD TRUST (BERMUDA) LIMITED

COURT:

LAW:

JUDGE(S):

CLAIMANT'S LAWYER:

DEFENDANT'S LAWYER:

Supreme Court of Bermuda

COMMERCIAL COURT CIVIL JURISDICTION

IAN R.C. KAWALEY CHIEF JUSTICE

Alexander Layton QC Ms. Lilla Zuill

Mark Cran QC Mr. Jan Woloniecki Mr. Nathaniel Turner Ms Michelle Ashton

FACTS OF THE CASE:

Dispute over funding for construction of an opera house in Lucerne commitment made by defendant to fund up to CHF 120 million whether contract formed under Swiss or Bermudian law if there were equitable claims termination of funding recovery of damages

SUMMARY:

Plaintiff/Claimant

OUTCOMES:

RULED IN FAVOUR OF:

PLAINTIFF/CLAIMANT

DEFENDANT:

DURATION (DAYS):

ISSUES:

RELEVANCE:

RULING:

RULING TYPE:

CASES CITED:

Join our pro membership and get all the details at your finger tips

Want to see full case details, including key arguments and claims? [Join Pro Membership] to unlock exclusive insights.

Discover the legal strategies and defenses used in this case. [Join Pro Membership] for full access.

How long did this legal battle last, and what key events happened? [Join Pro Membership] to find out.

Uncover the critical legal principles debated in this case. [Join Pro Membership] for in-depth analysis.

See why this case matters in Banking, Mortgages, and Financial Services. [Join Pro Membership] to explore its impact.

Find out the final judgment and its legal implications. [Join Pro Membership] to access the ruling.

Understand how this judicial ruling sets a precedent in law. [Join Pro Membership] for expert breakdowns.

See how past legal precedents influenced this case. [Join Pro Membership] to unlock the list.

Download Case Summary: 

pdf.png
AI Chatbox Anchor

Explore:

EPHESIANS 6:16

PT Satria Tirtatama Energindo v. East Asia Company Limited and Bali Energy Limited

2016

RE: C (VARIATION OF ACCESS ORDER)

2015

In the Matter of IPOC Capital Partners Limited and others

2007

Hindsight law can make mistakes. Consider checking original case studies

STIFTUNG SALLE MODULABLE and RUTLI STIFTUNG vs. BUTTERFIELD TRUST (BERMUDA) LIMITED

Dispute over funding for construction of an opera house in Lucerne commitment made by defendant to fund up to CHF 120 million whether contract formed under Swiss or Bermudian law if there were equitable claims termination of funding recovery of damages

bottom of page